Results
21-S-01 was awarded on May 17, 2022 to BMY Construction Group, Inc.
Bids for this project were opened on Thursday, April 14, 2021 at 2:00 p.m. on Zoom.
Bid Summary(PDF, 266KB)
Everyone who expressed interest in this project is listed on the Planholders List(PDF, 264KB).
Description
The work to be done consists of a renovation to the existing Sheriff’s Substation and Storage Building, which were recently constructed through Bid Package 1 to include but not be limited to: construction of a new Data Center located within the existing Storage Building, expansion of the existing Electrical Room located in the existing Substation Building, construction of new solar ready vehicle parking canopies. The associated work for these improvements may include mechanical and electrical work in the Data Center and Electrical Room, vehicle charging stations, concrete slabs, concrete pads, interior light gauge metal framing, and storefront glass. The base bid will include the new Data Center and expansion of the existing Electrical Room. The Carport Canopies and EV Charging Stations are included as additive bids.
The architect's estimate range is $3,300,000 to $3,600,000.
Location Map(PDF, 288KB)
Specifications and Plans
Notice to Bidders(PDF, 206KB) posted 2/15/2022
Project Manual(PDF, 5MB) posted 2/15/2022
Plans(PDF, 36MB) (36 MB) posted 2/16/2022
Addendum 1(PDF, 509KB) posted 03/04/2022
Addendum 2(PDF, 6MB) posted 3/17/2022
Addendum 2 - Specifications(PDF, 992KB) posted 3/17/2022
Addendum 3(PDF, 1MB) posted 4/11/2022
Supplemental Information
Requests for Clarification Responses updated 4/11/2022
Pre-bid Meeting
County staff was held on Zoom to discuss this project:
March 2, 2022 at 10:00 AM Pacific
Pre-Bid Conference Agenda(PDF, 123KB) posted 02/28/2022
Pre-Bid Conference Attendees(PDF, 75KB) posted 3/17/2022
Pre-Bid Conference Minutes(PDF, 108KB) posted 3/17/2022