The following list is comprised of paraphrased questions submitted by potential bidders or sub-bidders in writing via email, letter, and this form:
Request for Clarification Form - 20-S-02 Animal Control Center
These paraphrased questions and associated responses are not part of the contract documents and shall have no bearing whatsoever on the interpretation of the Standard Specifications, the Standard Plans, the Special Provisions, or the Plans. Nor shall they have any bearing whatsoever on the interpretation of other publications referenced therein.
Questions without answers may be posted here to indicate that we have received them before the deadline and we intend to respond.
Last updated: 8/26/2020 2:11 pm
Sheet E10.15 – low Voltage Details – This Plan sheet does not include any details. Please advise. (Ref#18230)
Remove E10.15 from the drawing set.
We have evaluated the schedule per section 005213, and 166 C/D is an unrealistic time frame. The project schedule should be more like 250-270 calendar days. This schedule is based on input from metal building manufacturers on how long it takes to design, permit, manufacture and erect. (Ref#18239)
We will not adjust the schedule at this time. See Addendum 01.
Soltek would like to enquire if The County has an anticipated NTP for Contract 20-S-02 Animal Control Center. (Ref#18328)
It is anticipated that an NTP will be issued on or before 8/31/2020.
The current specifications appear to be missing or have partial information about the items listed. Please confirm if these will be provided in forthcoming addenda... (Ref#18333)
Question Details RFC#18333
Please utilize baseline specs listed on the drawings and manufacturer’s recommended installation standards.
Drawing Number A10.11 details and plywood (Ref#18701)
Question Details RFC#18701
1. Refer to Details E15/1-A5.1, A14/1-A6.1, E14/1-A6.1 and J14-1-A6.2, change detail callout A1-D/A10.11 to A12-D/A10.11.
2. Refer to Detail A14/2-A2.1. Refer to Box Column at Grid B9, change wall call out from 10C to 15C.
3. Plywood fastening by others (structural engineer or Pre-Engineered Metal Building sub).
4. Refer to G0.1, General Notes, 01 11 13 Summary of Work, 1., Sentence 3 as noted "Drawing Divisions are not intended to divide the construction work by trade or contract".
5. Refer to Detail A14/2-A6.1, Building Section, Detail A5/A10.12 is called out on this detail.
These revisions will be addressed in Addendum 02.
Insurance requirements on this project are requesting $5 mil per occurrence and $10 mil aggregate, when industry standard is $1 mil per per occurrence and $ 2 mil aggregate. Can you confirm if the requested amount is accurate? (Ref#18713)
The insurance requirements as written are accurate.
In regards to project schedule, we concur with the statement made on RFI Ref#18239. The project is providing 166 CD for three Pre-engineered metal buildings. The allotted time will only be enough for design, engineering, submittals and procurement of the buildings. The remainder of the project including all interior buildout will be over the duration. We feel the allotted time frame of 166 CD is not achievable, the duration should be near 275 CD. (Ref#18714)
See Addendum 01.
Can you please provide details/specifications on the large animal enclosures show north of building 3? (Ref#18717)
The large animal enclosures will be provided and installed by County. Details and specifications regarding the large animal enclosures will not be provided at this time.
Drawing No. C1.1 Grading Plan Can you please provide call-outs & limits of site concrete scope? (Ref #18718 )
See Addendum 03.
Spec Section 31 20 00 pg 2 - Can you provide the Geotechnical Engineering Investigation Report as mentioned in above referenced specification section? (Ref#18720)
The Geotechnical report is published on the project website under Supplemental Information.
Drawing No. 1-A2.2; 2-A2.2; 3-A2.2 Legend keynote 21 reads, "provide allowance in bid for vapor alkalinity control system for floors receiving floor coverings." Will this allowance be provided by the owner? (Ref#18721)
No allowance is necessary. Include the price of sealant as shown in drawings in the bid cost. See Addendum 03
Can you please confirm Metallic Building as acceptable manufacture? Please see attached Metallic specifications. (Ref #18749)
Question Details RFC #18749(PDF, 240KB)
Upon review, Metallic Building looks to be an acceptable manufacture so long as the manufacture can comply with frame spans, slope, clearances and dimensions shown on the Drawings. Locations of columns, portal column locations, and rod bracing shall be placed only where shown on the drawings. Refer to Specification Section 133419 Metal Building Systems, Part 1 – General.
Sheet L1.1 notes chain link fence at north property line. Sheet A1.1 notes existing wrought iron fence in same location. Which is correct? (Ref #18897)
See Sheet L1.1 Layout Plan (Addendum 3), refer to fence on west side of property, "Chain Link Fence" note has been changed to "Wrought Iron Fence and Gate, S.A.P, typ." Also notes on west side of property line are no longer cut off.
Drawing No. 2-A2.2, 2-A7.1/4 Finish schedule calls for men's and women's shower and toilet area to receive WG2. A7.1/4 calls out 09.213 ceramic tile. Please advise. (Ref #18899)
Refer to A7.14/4/, refer to Detail 4C, Change keynote from 09-211 to 09-328.
Who installs all owner furnished items? (Ref #18900)
Owner to install owner furnished items unless otherwise noted.
Drawing No. 2-A9.1 Door jamb type Z:s is shown to be 3'4" wide. Schedule calls for 1-8 x 3-0. (Ref #18902)
The opening size is 1'-8" x 3'-0" as the door schedule indicates. The door needs a 3" overlap on the top, bottom and sides per detail A6,D6 andH6 on sheet A10.23
Drawing No. 3-S2.1, 3-S2.2 Note 15 is pointing to center footings. No note 15 in foundation reference notes. Please advise. (Ref #18903)
Note 15 has been added to Sheets 3-S2.1 and 3-S2.2. See Addendum 04.
Specification No. 015000-7 General requirements spec. calls for existing well in NE portion of site to be demolished. No well is noted on plans. (Ref #18904)
Spec Section revised. See addendum 03.
No SWPPP requirements or plans have been released. What are the requirements? (Ref #18905)
The County will be responsible for SWPPP and the enforcement of the SWPPP requirements. At this time, we do not have any additional information regarding SWPPP requirements.
Specification No. 00 72 00 pg 47- Insurance Req Are we allowed to use our umbrella total limit of $8,000,000 to meet both the General Liability & Auto Liability Requirement? (Ref #18906)
Yes, an umbrella policy could be used to meet the coverage limits.
Specification No. 015000-14 General requirements call for a 4'x8' project sign. What information will be required to be put on the sign? (Ref #18907)
Please omit the project sign. See Addendum 04.
Specification No. 01500-7 Note D- "Electric Power Service: Contractor may tap into site electrical service at the existing Building 2 main electrical room. Contractor must install power meter for monitoring construction power." Plans do not indicate existing building 2. Please advise. (Ref #18908)
Spec Section revised, See Addendum 03
Can we get a copy of PG&E rule 16? (Ref #18912)
PG&E will provide power to the transformer. Please bid work as shown in plans. Rule 16 will be provided during construction.
Drawing No. c1.1,c1.2 c1.1 calls for 3" pvc through sidewalk at multiple locations. C2.2 calls for 3x5 steel tubing at at least one of these locations. Please advise. (Ref #18916)
See Addendum 03.
No specs. for voice/data requirements were found (wire type, # wires per drop). No specs on security needs were found (camera or key-less entry). Please advise. (Ref #18917)
County and/or County Vendors will provide Voice/Data systems. Contractor shall coordinate with County Facility Services prior to and during installation.
Drawing No. E1.1 Keynote 7 refers to AT&T drawings. Can we have a copy of these? (Ref #18919)
Bid shall include AT&T conduits to the street. Final AT&T drawings will be provided during construction.
I noticed on the Bid Express website under the subcontractor information to fill out, some of the required fields on the site do not match the paper bid forms. The website asks for the email of the subcontractor and the paper form does not? Also the paper form says, "amount of bid or percentage of total cost" the website lists both items to be filled out. Please advise? (Ref #18946)
The Bid Express solicitation has been corrected to show "Amount of Bid" OR "Percentage of Total Cost." See Addendum #2 correcting the paper bid forms to ask for the email address of the subcontractor.
May we use the attached subcontractor listing? It is merely impossible to fill out dollar amount and/or percentage of subcontractor's bids at bid time. Please advise. (Ref #18956)
Question Details RFC #18956(PDF, 237KB)
No, you must use the supplied Section 004336 Subcontractor List to submit the subcontractor information either via Bid Express or paper form. If you do not include the subcontractor amount of bid or percentage of total cost and email addresses at the time of bid, we must receive your complete Section 004336 Subcontractor List within 24 hours of the bid opening. After the bid opening, Section 004336 Subcontractor List may be submitted via email as a pdf to DesignServicesfresnocountyca.gov.
I do not see anywhere on the drawings that call out or show fire extinguishers and or cabinets? Typically each building will require a certain amount of extinguishers per code, can you please provide specifications and locations? (Ref #18961)
The fire extinguishers are shown on the 3 buildings with the abbreviation FE and as defined on the G0.1 Cover Sheet under abbreviations. The call out for detail A10/A10.71 has been added to all locations on sheets 1-A2.1, 2-A2.1, and 3-A2.1. Refer to Detail A10/A10.71 add the Manuf. and Model number. See Addendum 04.
Drawing No. E1.1/E2.2 Specification No. 283100 Does the Fire Sprinkler Monitor System require deferred approval? (Ref #18966)
The fire sprinkler monitor system requires deferred approval by the installing contractor.
Drawing No. A9.1 Plans call for a "storefront louver." There is no spec for this item. Kindly requesting a spec on the material and finish, and whether to be custom made? (Ref #18984)
Refer to Sheet 2-A9.1, refer to Detail K5, refer to Window Type 3, see revised dimensions and note 08.198, refer to keynote, add keynote 08.198. Addendum 03.
Doors 5a, 12a and 18a note Automatic entrance doors but there is no spec on the auto operators or the accessories. Please advise (Ref #18985)
Refer to Sheets 1-A9.1 at doors 5a and 19b, 2-A9.1 at door 18a and 3-A9.1 at door 22a. Add the Manufacturer and Model for Auto Door Operators.
Drawing No. 1.A6.1Specification No. DIV. 9 Sheet 1.A6.1 on column line A refers us to A 10.11 detail A12D. Exterior soffits look like metal stud but is called as pre-engineered building components, please advise that this is correct? (Ref #18997)
Refer to G0.1, refer to General Notes, refer to 01 11 13 Summary of Work, refer to note #1, Sentence 3 "Drawing Divisions are not intended to separate the work by trade or Contract."
Drawing No. 1-A3.1,A10.91/A10 Detail H14 refers to structural plans for the sunscreen attachment. No attachments shown on structural plans.(Ref #19005)
Omit sunscreen. See Addendum 04.
Drawing No. 1-A5.1 Note 5.08 calls for sunscreen to be galvanized. F10/A10.91 show stainless steel. Please advise. (Ref #19007)
Omit sunscreen. See Addendum 04.
Drawing No. 3-A9.1 Door 11b- Coiling door. No spec. or width found. Please advise. (Ref #19008)
Utilize Pre-Engineered Buildings Overhead Door, Model 620S. Size Jamb for +/- 1402 lbs. See Addendum 04.
Drawing No. H14/A10.91 Detail calls for cement plaster. Could not find any other details to define limit of plaster. Please advise. (Ref #19009)
Omit sunscreen. See Addendum 04.
Drawing No. E10.11Specification No. 260500 Per Spec Section 260500 2.01.I, we are to use "MC Cable for branch circuits with EMT Home Runs". Per the engineer’s plans and the electrical symbol list on E10.11, branch circuit is drawn as being in ¾"min. conduit. Please confirm that MC cable is acceptable for all branch circuitry. (Ref #19026)
The specifications call for a threaded galvanized rigid steel conduit system installed throughout, except where noted otherwise. The 3/4" min. in the symbols applies to any raceway inside a building. MC cable may only be used for local branch circuiting; e.g., from a box over an office to the outlets in that office. The homerun from the box in the example office back to the panel shall be EMT. For this project specifically, you will mostly have EMT in walls and attic spaces everywhere except where the final branch circuit connections spider out to outlets and light fixtures in MC cable. Any exposed conduit below 96" would be GRS. Underground runs would be 1" min. schedule 40 PVC, with steel ells and risers on the site. See Addendum 04.
Drawing No. 2-A9.1,H6/A10.23 All doors in frame type Z:s are called to be wood on finish schedule. Detail H6/A10.23 calls for insulated galvanized sheet metal. Please advise. (Ref #19029)
1.) Refer to Sheet 2-A9.1, refer to Door Schedule, refer to all "Z" frames, change frame material to AL, change Door Size to 17" x 34", shown clouded with Delta 3.
2.) Refer to Sheet 2-A9.1, refer to Legend, Add note 4 for coordination of Guillotine Door Size with Specification on Detail D6-A10.23, shown clouded with Delta 3.
3.) Refer to Sheet A10.23, refer to Detail D6-A10.23, add Specification and Manuf. For Guillotine Doors, shown clouded with Delta 3.
4.) Refer to Sheet 2-A9.1, refer to Door Schedule, refer to note 10, add call out A12-A10.22.
See Addendum 03.
Drawing No. 1-A2.1 On gridline B & 3.5 , it call out D8/A10.11 Typ. at office number 8 wall. This details is for Interior column. Can you provide the correct detail/call out? (Ref #19041)
Refer to sheets 1-A2.1, 2-A2.1, 3-A2.1, add call outs for Interior Wall Base Details. Interior Wall Base D8-A10.11 occurs at all Kennels (where Cats and Dogs are housed). Interior Wall Base Detail G12-A10.13 is typical at rooms that are not Cat or Dog Kennels (where Cat or Dogs are housed). All changes clouded with Delta 3. Refer to sheet A10.13, add detail G12-A10.13 for wall Interior Wall Base Detail at locations that do not house cats or dogs, shown clouded with Delta 3. See Addendum 03.
Drawing No. 1-A2.2 It calls out for WGx for all walls at restrooms and there is no WGx on the schedule. What is the finish for the restroom walls? (Ref #19042)
Refer to Sheet 1-A2.2, Refer Toilets 16, 20, 21, and 23 change "WGx" to "WG2" shown clouded with Delta 3. See Addendum 03.
Drawing No. 1-A2.1 It refers to elevation 2 & 3 on 1-A9.1 at Dispatch room 12. There are no 2 & 3 elevations on 1-A9.1. Can you provide the correct elevations? (Ref #19043)
Refer to Sheet 1-A9.1, refer to detail K14, add Detail Callouts 2/1-A9.1 and 3/1-A9.1, shown clouded with Delta 3. See Addendum 03.
Specification No. 015000 - Temp Facilities Do we need to include a job trailer for the county project manager? (Ref #19044)
No
Drawing No. 1-A2.2 Ceiling in room 3 shows ACT1 and reflected ceiling plan shows gypboard. What is the correct ceiling type? (Ref #19045)
Refer to Sheet 1-A2.2, refer to room 3, change the Ceiling finish to "P1" shown clouded with Delta 3. See Addendum 03.
Drawing No. 2-A2.2 In room 17 Toilet - it has a symbol for linoleum flooring but it calls for concrete sealer. This room also calls for no ceiling but reflected ceiling plans shows gypboard. Can you please provide desired finishes for this room? (Ref #19046)
Refer to Sheet 2-A2.2, Room 17 Toilet, change the ceiling finish to "P1" and Flooring finish to "LN1", shown clouded with Delta 3. See Addendum 03.
Drawing No. 2-A2.2 In room 18 & 19, can you please confirm AC1 is the same as ACT1 and AC2 at room 8 is the same as ACT2? (Ref #19047)
Refer to Sheet 2-A2.2, refer to Rooms 18 and 19, change "AC1" to "ACT1", shown clouded with Delta 3. See Addendum 03.
Drawing No. 2-A2.2 In room 5 & 7 -it shows painted ceilings as if it's gypboard, but on reflected ceiling plan it shows acoustical tiles. Please clarify. (Ref #19048)
Refer to 2-A2.2 Finish Plan and Schedule, refer to Room 5 and 7 Mens and Womens Lockers, change Ceiling from "P1" to "ACT1", shown clouded with Delta 3. See Addendum 03.
Drawing No. 2-A7.1 Numerous keynotes state owner furnished items and they don't have "NIC" written next them: Does this imply that contractor is to install these items? (Ref #19050)
Owner furnished items to be installed by owner. Refer to Sheet G0.1 Project Data, refer to abbreviations, refer to "NIC" and add definition. See Addendum 04.
Drawing No. 3-A2.2 In Room 2 Cat Intake and Prep - it has a symbol for concrete sealer but calls for polished concrete. Please clarify. (Ref #19052)
See Sheet 3-A2.2, refer to Room 2 Cat Intake and Prep, change "PS1" to "CS1", shown clouded with Delta 3. See Addendum 03.
The Area at the Large Animal Enclosures shall be graded clean soil with no other materials added.
Drawing No. L-1.1 Is the DG to be placed under large animal enclosures? if not, what is the finish material at this location? (Ref #19053)
The Area at the Large Animal Enclosures shall be graded clean soil with no other materials added.
Drawing No. 1-S2.1 Administration partial foundation plan note 9, refers to detail 14/S4.1. There is no detail 14 on sheet S4.1. Can you please provide this detail? (Ref #19056)
Detail 14 has been provided on Sheet S4.1. See Addendum 04.
These RFI (Request For Information) answers provided as supplemental information states - "Not part of the contract documents". Will these RFI's be issued in an addendum? (Ref #19058)
Yes, RFC information will be included in an Addendum as appropriate.
How do you get into the bid to do it online? I tried the link but you have to sign in. Do we have to be pre-registered? (Ref#19060)
This project does not have a prequalification process. If you need more information about using Bid Express, here are some resources on our website:
Electronic Bidding
Please contact us at DesignServicesfresnocountyca.gov if you have any questions about how to set up your account, how the software works or help navigating or using the Bid Express website. Please note that you can submit a bid using Bid Express and revise or withdraw it before the deadline.
Drawing No. A10.91 Can you please specify sunscreen framing material (Steel or Aluminum)? (Ref #19095)
Both Steel and Aluminum are acceptable materials.
Drawing No. A1.1 & L3.1 Can you clarify the areas that are requiring synthetic turf? Sheet A1.1 calls out two additional areas, but sheet L3.1 does not show these areas requiring turf. (Ref #19130, 19133, 19154)
Extend of synthetic turf installation shown on Sheet L3.1 has been revised to match extent of synthetic turf installation on Sheet A1.1. See Addendum 04.
Specification No. General Conditions There is a requirement for Professional Liability Insurance, if the contractor is a licensed professional or employs professional staff, (i.e., architect or engineer). Will this type of insurance be required for the bidding General Contractor?
Is an excess / umbrella policy acceptable to achieve the 5M occurrence and 10M aggregate and auto liability as required? (Ref #19151)
No, general contractors are not required to have Professional liability insurance. Yes, an umbrella policy could be used to meet the insurance limit requirements.
Can our synthetic product be approved as an equal for what you have specified? (Ref #19172)
Question Details RFC #19172 SYNLawn Pet Platinum(PDF, 2MB)
Pet Platinum is acceptable.
Specification No. 015000-4 Under temporary facilities it notes "For fences and vision barriers, provide exterior type, minimum 3/8" thick plywood." Does the temp. fence have to have 3/8" plywood installed as a vision barrier? (Ref #19228)
Yes.
Drawing No. 1-A2.1 Note 10.17NA(2) fire department locks for gates and (1) knox box is called out but no model number, please provide for proper pricing. (Ref #19229)
Refer to Sheet 1-A2.1, refer to keynotes, change keynote 10.17 adding the Fresno County Fire Department Policy 706 reference. Addendum 03.
Drawing No. 1-A2.1 & 1-E2.2I What are the electrical provisions for the Automatic Entrance Doors? Do the automatic entrance doors have a push paddle per Det. A4/A10.81? (Ref #19250)
Refer to Electrical for Auto Door electrical provisions. Refer to sheet 1-A9.1, refer to Doors 5a & 19b, refer to sheet 2-A9.1, refer to door 18a and refer to sheet 3-A9.1, refer to door 22a, refer to Legend, add note referring to A4/A10.81 for Auto Door Operators. See Addendum 03.
Drawing No. 2-A7.1 Keynote 10.231 calls for an ADA bench. Is there a specified. material for these benches? (Ref #19253)
Refer to 2-A7.1, refer to keynotes, change note 10.231 to 01.52. Refer to Elevation 5B, back added to the bench and change keynote to 02.52. Refer to Enlarged Floor Plan, change note 10.231 to 01.52. Refer all shown clouded with Delta 3. See Addendum 03.
Drawing No. A10.22 Detail A4 & D4 - Are these details applicable to this project? They are not called out on the door schedule(s). (Ref #19254)
Refer to Sheet 1-A9.1, 2-A9.1, and 3-A9.1, refer to Legend, add note for location of "Hardware, door stops, at interior doors provide per K8/1-A9.1, (2-A9.1, 3-A9.1)". Provide Hardware, door stops per detail A4 or D4 at exterior doors where required by the owner.
Drawing No. A10.21 Detail A12 Threshold shows 1/2" expansion joint / Waterproofing. Can you specify the product used for the waterproofing? is this applicable only at door openings? (Ref #19261)
Refer to Detail A10.21, add specifications of expansion joint. See Addendum 03.
Drawing No. 1-A2.1 & 1-A9.1 Door schedule shows (Dispatch Room) door#12a having a Automatic Entrance Door. Can you confirm if this is accurate? If so, Please provide operator and power data as applicable. (Ref #19266)
Automatic Entrance at door 12a has been removed. See Addendum 03.
Drawing No. A10.21 Detail A8 Sheet A10.21 Detail A8 calls for "sound blanket" at window and door frames. Can you please clarify the material intended, is this a fiberglass or steel wool material? (Ref #19270)
Refer to sheet A10.21, refer to Details A8, D8, D12, K8 and K12, delete the Insulation inside the Timely Frames. Refer to Sheet A10.11, refer to Detail A1 Wall Types, add the following for note # 9:
"9. SOUND BLANKET AT KENNELS AND OFFICE TO BE ASTM C665, TYPE I; PREFORMED GLASS FIBER, FORMALDEHYDE-FREE, UNFACED, FLAME SPREAD LESS THAN 25, ASTM 84, SMOKE DEVELOPED RATING: MAX 50"
See Addendum 04.
Drawing No. A10.91 Detail H14 calls out 5"x5"x1/2" column see structural. There are no footings or columns shown for the shade canopy on the structural. Can you provide footing/rebar details, connection details and height of column? (Ref #19306)
Omit sunscreen. See Addendum 04.
Drawing No. L5.1, L2.0 The models of irrigation controller, remote control valve, backflow preventer, flow sensor, quick coupler, lateral line, rain sensor, etc..that are shown on specifications sheet L5.1 conflicted with irrigation legend. Please clarify. (Ref #19351)
Sheets L2.0, L2.3, and L5.1 have been revised. See Addendum 03
Drawing No. L2.0 Please provide size for Backflow preventer (Ref #19357)
Added to sheet L2.0, see Addendum 03
Drawing No. L1.1 Please provide specifications for non-stabilized DG, stabilized DG, crushed granite that was shown on sheet L1.1 (Ref #19358)
Detail 1/L4.1 has been revised to show specification, availability, and installation steps for the Stabilized DG, Non-Stabilized DG, and Crushed Granite. See Addendum 04.
Drawing No. L1.1 & L4.1 Paving legend sheet L1.1 shows Decomposed granite is "SUNSET GOLD". However, note 3 detail 1 sheet L4.1 shows "PATHFINES CALIFORNIA GOLD". Please clarify. (Ref #19359)
Detail 1/L4.1 has been revised to show Sunset Gold Path Fines available from Lygnso Garden or Equivalent as the type of decomposed granite. See Addendum 04.
Drawing No. L3.2 Please provide detail/installation for 5G vine JASMINIUM POLYANTHUM (Ref #19360)
A Vine Installation detail was added to Sheet L4.1. See Detail 4/L4.1. See Addendum 04.
Drawing No. L2.0, L3.2, L5.1 & L5.2 Comparing the drawings with specifications sheet L5.1, L5.2, please confirm which one will take precedence. (Ref #19361)
Sheets L2.0, L2.3, and L5.1 have been revised. See Addendum 03
Drawing No. A10.11 Detail A1 wall type (10C & 11C), states " Pre-engineered buildings, accessories, wall panel, insulated." Are these insulated "sandwich" panels? Or is this note just referring to 1" rigid insulation under standard metal panel siding? (Ref #19371)
Refer to Sheets 1-A2.1, 2-A2.1, and 3-A2.1, add notes "Face of concrete at Exterior Walls typ."
Refer to A10.11, refer to details A1, A12B, A12D, K8, and K12; and refer to sheets A10.12 details A5 and A12; and refer to Sheet A10.21 details A4, D1, D4, G1, and G4; and refer to Sheet A10.22 details A1, D1, and G8; and refer to Sheet 10.23 details A6, A12, D6, D12, and H6; change the exterior wall sections to Pre-Engineered Metal Building, Wall Panel, R16, 2" thick, delete rigid insulation and note that the face of Pre-Engineered Metal Building, Wall Panel, Insulated, R16 is flush with the face of concrete.
Drawing No. A10.11 Detail A1 Wall type (Exterior walls) calls out what appears to be single layer of vapor barrier. On detail A12, it calls for double layer at plywood. On details G1, G4 on sheet A10.21 and details D1 & G8 on A10.22 shows what appears to be double layers. How many layers of vapor barrier do we need on exterior walls? (Ref #19372)
Refer to Detail A12D/A10.11, delete "double layer at Plywood." Refer to Detail A5/A10.12, delete "double layer at Plywood." Refer to Details G1/A10.21 and G4/A10.21, remove double layer of vapor retarder. Refer to Details D1/A10.22 and G8/A10.22, remove double layer of vapor retarder. See Addendum 04.
Drawing No. E1.1 Site Plan Specification No. 26 Where do we connect AT&T and PG&E lines. Need the Rule 16 Drawing and AT&T point of connection for Sheet Notes 1 and Sheet Notes 7 (Ref #19397)
AT&T lines and connections will be completed by Fresno County. PG&E will bring power to the transformer on site. Contractor shall anticipate connecting power at the transformer. Rule 16 Drawings will be available during construction.
Drawing No. Admin Building no. 1 - 1) Window types 1 and 2 show both storefront details and Timely frame details.
Are these windows storefront or Timely?
(Ref #19411)
Window Types 1 and 2 are Timely frames on the interior windows and Storefront on the Exterior. See Addendum 04.
Drawing No. Admin Building no. 1 - 2) Wood door are listed as plastic laminate, what is the plastic laminate number or color? (Ref #19412, #19416)
Owner to select color. Contractor to provide color samples for selection with submittals.
Drawing No. Meet & Greet Building no. 2 Door type 01.s elevation shows a swinging door. Detail H6 & D6/A10.23 shows a sliding transfer door insulated by misc. specialties. Door schedule lists wood doors, are these doors wood or insulated transfer doors by misc. specialties? (Ref #19413)
Refer to Sheet 2-A9.1, refer to detail E5 Door Panel Types, add Door Type 11:S. Refer to Sheet 2-A9.1, refer to detail A14 Door Schedule, change Door Type Z:S frame type to HM. Refer to Sheet 2-A5.1, refer to details A15 and J15, add the door swing to up and down rather than swing. See Addendum 04.
Drawing No. Meet & Greet Building no. 2 The door frame types Z:S lists size 1'-8" x 3'-0" on the door schedule 2-A9.1. Elevation Z:S same page lists frame width at 3'-4" and no height.
Which is the correct width and height for this frame type? (Ref #19414)
See Addendum 03 for Door Type Z:S for height and coordinating with door type specification.
Drawing No. Intake and Food - Pre Opening numbers 9a, 10a & 10b are listed as panel type 01:D there is no panel type 01:D on the door schedule page 3-A9.1. Please provide panel type 01:D. (Ref #19415)
Panel type 01:D has been added to sheet 3-A9.1 detail K14 – Door Panel Types. See Addendum 04.
Drawing No. Intake and Food Prep - Elevations for window types 34 & 2 are not shown. Please provide. (Ref #19417)
Revise Window Type 34 callouts to Window Type 6. Revise Window Type 2 callouts to Window Type 5. See Addendum 04.
Drawing No. A10.11 Specification No. drywall Wall types per A1/A10.11 show gypsum wall board but there is no Gypsum Board Specification . Will one be provided for Interior Gypsum Board and Exterior Gypsum Sheathing ? (Ref #19448)
Specification Section "092900 – Gypsum Board" has been added to bid documents with Addendum 04 revisions. Refer to sheets 1-A7.1, 1-A8.1, 2-A7.1, 2-A8.1, 3-A7.1, and 3-A8.1, refer to Interior Legend, add notes 10 for water resistant gypsum board locations at all rooms that house dogs and cats and at toilets.
I am reviewing the Request for Clarification responses on the website, and I am a little confused. Where do I find the reference # or responses that the following question is referring to? (Ref #19471)
The Ref# is the Request for Clarification number / RFC number / Submitter ID. It is the number assigned to your question when you submit one using the form above and is listed as the Submitter ID on the confirmation email. This number helps us keep track of your questions.
"Drawing No. A1.1 & L3.1 Can you clarify the areas that are requiring synthetic turf? Sheet A1.1 calls out two additional areas, but sheet L3.1 does not show these areas requiring turf. (Ref #19130, 19133, 19154)" - What is Ref# 19130, 19133 & 19154? (Ref #19472)
Essentially the same question was submitted by different people. Each of them received a RFC#/Submitter ID/Ref# for their question, but we paraphrased and combined each question into one.
Also, the other Request for Clarifications that do not have responses, where can I find those responses? Or when do you anticipate the responses being posted on the website? (Ref #19473)
See instructions above (top of the RFC Responses web page): "Questions without answers may be posted here to indicate that we have received them before the deadline and we intend to respond. Due to staffing issues, delays are anticipated in responding to outstanding or new Requests for Clarification (RFCs)."
Is there or will there be a demolition plan? (Ref #19482)
There is no Demolition Plan.
The supplied soils report does not have the boring logs. Will those be made available? (Ref #19483)
The boring logs (14 MB)(PDF, 13MB) will be made available for reference on the project website.
Please provide a specification for the Transfer Doors. Also note that the standard width for a guillotine door is 17" up to 34" high. Any larger size would need to be purchased as a custom made door. (Ref #19500)
Refer to RFC 19029, 19413, and 19414 responses.
Drawing No. 1-A2.2 Specification No. 84113 One question about color for "Aluminum Entrances and Storefront".
On page 1-A2.2 (finish schedule), 084113 shows storefront color: Anodized Black color (Kawneer Anodize finish n.29).
(All 3 buildings show same color).
Project Manual, however, Section 084113 (page 6) under finishes, shows Clear Anodized Class 2 (AA-M12C22A31).
Please advise on correct color for Storefront. (Ref #19623, 19652)
Exterior storefront frame color to be Anodized Black (Kawneer Anodize finish No. 20).
Drawing No. 1-A8.1Per 5A/1-A8.1, we see a half height plastic laminate wall with solid surface cladding per finish notes CW1 & SS2. Detail E11/A10.62 references a portion of that wall to have a hammered metal finish and we do not see where this applies or is specified, please clarify the finish of the half height wall. (Ref #19625)
Refer to Detail E11-A10.62, delete note regarding hammered metal finish and add arrow to high counter. See Addendum 04.
Drawing No. 1-A9-1 Page 1-A9-1 (door 12a) shows "yes" for Panic. This is an interior door. Please confirm on panics. (Ref #19627, 19653)
Remove panic hardware from door 12a. See Addendum 04.
Drawing No. 1-A9-1 Page 1-A9-1 (door 12a) shows "Automatic doors" under comments. From plans, it shows a swing door. Please confirm (Ref #19628, 19654)
Refer to RFC 18985 and Addendum 03.
Drawing No. 1-A9-1 Page 1-A9-1 (door 5a) shows "Automatic doors" under comments. From plans, it shows double swig door. Please confirm. (Ref #19629, 19655)
Door 12a is not an Automatic Door. See Addendum 03.
Drawing No. 1-A9-1 Page 1-A2-1 (Dispatch 12) walls with glass. Assuming that the wall with glass are "Timely" system. Will include installation of glass only with the proposal. Please confirm on this wall with glass. (Ref #19630, 19656)
Door 12a is a Pre-Finished Metal Door Frame with Glazing, see sheet 1-A9.1, Detail A14 Door Schedule, refer to Door 12a, Frame Type is PM.
Refer to Sheets 1-A9.1, 2-A9.1, and 3-A9.1. Refer to legend, add glazing symbol. Refer to Sheet 1-A9.1, refer to details A5 and K14, add glazing symbols. Refer to Sheet 2-A9.1, refer to details A6 and K5, add glazing symbols. Refer to Sheet 3-A9.1, refer to details A5 and H14, add glazing symbols. See Addendum 04.
Drawing No. 2-A9-1 Page 2-A9-1 (door 18a) under comments shows automatic door. Plans shows single swing door. Please confirm. (Ref #19631, 19657)
Refer to RFC 18985 and Addendum 03.
Drawing No. L2.0 Remote control valve #1 should be for dripline and remote control valve #2 should be for bubblers. Please clarify. (Ref #19642)
Yes, this is correct.
Drawing No. 3-A9-1 Page 3-A9-1 (doors 9A, 10A, 11A) show to be wood doors. From drawings it looks like these doors are aluminum store font doors. (Ref #19650)
Refer to sheet 3-A9.1, refer to door 9a, 10a, 11a, and 18b, change the frame material to AL. Refer to sheet 3-A9.1, refer to detail H14, refer to Door frame Type L:D, delete the door swing. Revise title of detail H14 from "Door Panel Types" to "Door Frame Types." See Addendum 04.
Drawing No. 3-A2-1Page 3-A2.1 All windows marked (34) look like windows (6) from window schedule. Please confirm. (Ref #19651)
Refer to sheet 3-A2.1, change all window 34 callouts to 6, change windows at Rooms 9 Laundry and 10 Food Prep to Window Type 5. See Addendum 04.
Drawing No. L-1.1 On the far north side of property, there is an area that seems to be DG based on the texture pattern used from the key, but there is a call out that says "compacted soil". Please clarify which surface is to be used. (Ref #19778)
Sheet L1.1 has been revised to show the area on the far North side of the property as compacted soil as called out. It has been designated a unique hatch pattern and added to legend. See Addendum 04.
I received this notice on Friday and thought it was for addendum #4 but Bid Express shows 3 addendums, please advise? (Ref #19779)
Question Details RFC 19779(PDF, 129KB)
The email was automatically sent to you from Bid Express. It is not a numbered addendum (example: Addendum #03) issued by the County of Fresno for this project and does not need to be acknowledged in the Acknowledgment of Addendum section to be considered responsive.
Drawing No. L-1.1 There are three types of DG listed in the key. Is the "crushed granite, color B, grey" to be stabilized? (Ref #19780)
Sheet L1.1 Legend has been revised to show the crushed granite, color B, grey non-stabilized. See Addendum 04.
Drawing No. L-5.2 There doesn't seem to be any written specs included for the Landscape portion of the project, like the other divisions of work that are listed in the specs table of contents (example: "Earthwork"), other than in the plans, sheet L-5.2. Is this correct? (Ref #19783)
Yes, all Landscape specs are on the drawings.
Drawing No. L-3.2 In the "Plant Palette", on sheet L-3.2, the Lecucodendron 'Safari Sunshine' is listed, but is nowhere on the plans. Are any to be included? (Ref #19784)
Leucodendron ‘Safari Sunshine’ is no longer being used. See Addendum 04.
Drawing No. L-4.1 Is filter fabric to be placed under all GOLD decomposed granite surfaces, both stabilized and non-stabilized, or only stabilized areas? Please clarify. (Ref #19786)
Filter fabric to be placed under stabilized only areas.
Did you know that the Polished concrete by Bomanite Vitraflor is a proprietary product for only the Heritage Bomanite company to do? They won’t even sell this product or let me buy this product. Why is this product spec’ed on this project that is prevailing wage? You will be getting a price from only one source on this spec. (Ref #19793)
Spec Section "033543 – Polished Concrete Finishing" has been added to the bid documents with the Addendum 04 revisions. Please utilize the standards in this section for selecting a product. Finish Schedules on the drawings will be updated to specify Polishing and Gloss levels.
Is there Specifications Section for the Chain Link Fence, Gates and Hardware? (Ref #20032)
No Specification Section.
Addendum #3 L-1.1 West side calls for wrought iron fence. Is there Specifications and details for the wrought iron fence? (Ref #20034)
Wrought Iron Fence is Existing.
Sheet G1.1 Keynotes # 32.88 Is there specifications for the electrical gates and battery up? (Ref #20035)
No Specification Section.
E1.1 If the gate shown on Sheet G1.1 is an electrical opened gate there isn't conduits or power shown to the gate. (Ref #20036)
Gates entering the site are manually operated. No electrical connection is required.
Is the owner providing and paying for the construction surveying and construction staking. (Ref #20051)
The County will not be paying for Construction Survey or Staking.
Is the owner providing and paying for the PG&E Rule 16 Fees and is the PG&E Rule 16 Design been completed? (Ref #20054)
Rule 16 is being processed by the County and is in Design with PG&E.
Per addendum 4 where they clarified a 2" insulated panel but there is still missing information in regards to a corrugated wall panel, see attached CBC steel attached profiles most commonly used. The detail per cut on sheet A10.11 calls for a concealed fastener but AWIP does not offer a corrugated panel as shown. Also, is the back sheeting of the parapets going to be finished with insulated panel or just single sking "R" panel? (Ref #20059)
The insulated wall panels should extend to the top of the parapet without seams.