Request for Clarification Responses

East Reedley Bridge Replacements

Supplemental Information - Not Part of the Contract Documents

The following list is comprised of paraphrased Requests for Clarification (RFC) submitted by potential bidders or sub-bidders in writing via email, letter, and this form:

24-07-C Request for Clarification Form

These paraphrased questions and associated responses are not part of the contract documents and shall have no bearing whatsoever on the interpretation of the Standard Specifications, the Standard Plans, the Special Provisions, or the Plans. Nor shall they have any bearing whatsoever on the interpretation of other publications referenced therein.

Questions without answers may be posted here to indicate that we have received them before the deadline, and we intend to respond. 

Last updated: June 26, 2024 2:00 PM Pacific

 

Drawing No. CD-2, CD-3 AND CD-5
Can existing topographic grades or cross sections be provided to perform accurate earthwork take off? (RFC 2407-2 submitted 6/25/2024)

The Channel Cross Sections are posted on the project website under "Supplemental Information". Response date: 06/26/2024