Specification No. 39-2.01C(8) Leveling
Will a leveling course be required prior to paving the Overlay areas? (RFC 2323-1 submitted 2/8/2024)
No. Response date: 2/14/2024
Specification No. Bid Item #11 - GPR
Aside from what Underground Service Alert will locate, what is the intent for GPR Services? (RFC 2323-2 submitted 2/12/2024)
See Specs. Section 5-1.20G, PG&E Existing Gas Lines and other utilities. Response date: 02/13/2024
If the contractor elects to pave the minor HMA (misc areas, shown on sheet 23) with the paving machine concurrently with the mainline paving operations, is the County going to pay these areas under bid items 26 & 27 or is the County going to pay for this work under bid item 25? (RFC 2323-3 submitted 2/14/2024)
See Addendum #1. Wing out will be paid as part of the HMA bid item #25 HOT MIX ASPHALT (TYPE A 3/4" GRADING) as it will be most likely constructed with the paving machine concurrently with the mainline paving operations. Response date:02/16/2024
Per plan sheet 23, the wing-outs are to paid under the HMA bid item, but what about the areas beyond the wing-outs, will these areas be paid under the minor HMA items no matter how the HMA is placed even if it is concurrent with mainline paving operations? (RFC 2323-4 submitted 2/14/2024)
Yes. All areas requiring more than 2’ wide strip of pavement is considered Misc Areas and will be paid under bid item 26 MINOR HOT MIX ASPHALT (FOR DIKES AND MISC. AREAS) and 27 PLACE MINOR HMA (MISCELLANEOUS AREAS) Response date: 02/16/2024
It is our understanding that there will be no cost associated with the required PG&E stand-by staff, can you please confirm this is the case? (RFC 2323-5 submitted 2/14/2024)
PG&E will provide stand-by staff at no cost to the County or Contractor. Response date: 02/16/2024