Request for Clarification Responses

Edge Line Striping

Supplemental Information - Not Part of the Contract Documents

The following list is comprised of paraphrased Requests for Clarification (RFC) submitted by potential bidders or sub-bidders in writing via email, letter, and the Request for Clarification Form (archived). 

These paraphrased questions and associated responses are not part of the contract documents and shall have no bearing whatsoever on the interpretation of the Standard Specifications, the Standard Plans, the Special Provisions, or the Plans. Nor shall they have any bearing whatsoever on the interpretation of other publications referenced therein.

Questions without answers may be posted here to indicate that we have received them before the deadline and we intend to respond. 

Last updated: March 14, 2024 @ 9:00 AM

 

Specification No. Section 17 Clearing and Grubbing
What exactly is the County looking for regarding "Clearing and Grubbing"? (RFC 2310-1 submitted 03/12/2024)

The work involved in “Clearing and Grubbing” includes, but is not limited to, providing all labor, supervision, equipment, incidentals and related items necessary to remove and dispose objectionable materials from the edge line striping work area such as vegetation and accumulated dirt as specified in the Standard Specifications Section 17-2.01. Response date: 03/14/2024