Request for Clarification Responses
22-24-J 22-25-J 22-26-J Class A General Engineering Job Order Contract
Supplemental Information - Not Part of the Contract Documents
The following list is comprised of paraphrased Requests for Clarification (RFC) submitted by potential bidders or sub-bidders in writing via email, letter, and this form:
These paraphrased questions and associated responses are not part of the contract documents and shall have no bearing whatsoever on the interpretation of the Manual. Nor shall they have any bearing whatsoever on the interpretation of other publications referenced therein.
Last Updated: 4/5/2023 12:45 pm
If we submit our factor and then the material prices skyrocket, will that be factored in later during the review? (RFC 52250 submitted 3/21/2023)
See Article IV. Compensation in the Agreement under “Material price spike adjustment.” Response date: 03/22/2023
Will contractors be using the eGordian web-based platform/app? (RFC 52256 submitted 3/21/2023)
Yes, contractors will be using the eGordian web-based platform. Response date: 03/22/2023
If awarded, contractors must provide a bond in the amount that may possibly be awarded to them, but if there’s no work, is there a clause in the agreement that reimburses the bond? What is the amount of the bond that will need to be provided? (RFC 52269 submitted 3/21/2023)
There will be no reimbursement for bonds. Refer to the Notice to Bidders under “Minimum and Maximum Contract Values” for bond amounts. Response date: 03/22/2023
What is the amount of the bid bond that the contractor has to provide at the time of bidding? (RFC 52285 submitted 3/22/2023)
The amount of the bid bond is $25,000. See Addendum #1. Response date: 04/05/2023